Today I received email from our friend John at the Land Redevelopment Office. He has been keeping us updated regularly (every 2 days or so).
I can’t summarize the good news better than his email to me, so here it is:
More updates on 1680-1684 E. Main:
The Building Department issued an order to demolish structure and we are working to comply with that order. Â Â We received a few bids today, selected a contractor, and are waiting for three things:
1.       Approval of an emergency expenditure of funds and contract
2.       Permits
3.       Sign-off from Ohio EPA for emergency demolition
I expect the demolition to start early next week, if not sooner.
John